Case Study

CityLink Tulla Widening Gantry Rectification Project

  • ClientCPB Contractors
  • StartMarch 2020
  • Value$30m
  • CompleteSeptember 2020

Following the collapse of a large sign onto the Tullamarine Freeway in 2019, this project replaced the N03-15 gantry on CityLink, as well as rectifying and strengthening 15 other gantries between the Bolte Bridge and Tullamarine Airport.

Doing 'it' better

Finished ahead of schedule with zero lost-time injuries

FSC ScopeExpand+

  • Acting as the project’s ‘Nominated Authority’ (approved by Transurban and the Department of Transport)
  • Managing welding supervisors, NDT technicians, crane crews, welders, painters and electrical installation crews
  • Guiding and monitoring a 20-strong team to rectify gantries
  • Overseeing the fabrication of the steel strengthening supports and components needed to rectify the gantries, as well as the new gantry

ChallengesExpand+

  • Parts weighing up to 140kg
  • Working with the fabrication workshop to ensure each component was designed and made to exacting quality standards
  • N03-15 gantry had to be installed in a short road closure window – with no overruns
  • Extensive planning to install gantry components with cranes during the road closure

SmartsExpand+

  • Using photogrammetry to scan the 15 gantries needing rectification
  • Ensured every new component was made to the unique specifications of the gantry it was intended for, ensuring an exact fit, first time
  • After installation, each gantry was scanned again to become the job’s ‘As-builts’

AchievementsExpand+

  • Providing Transurban, the Independent Reviewer and Department of Transport with comprehensive daily progress reports.
  • Accuracy and detail in the reports created a strong bond of trust, meaning the parties only visited the site four times during the entire project – each time providing positive feedback.

PerformanceExpand+

  • Safety: 0 Lost Time Injuries
  • Program: Finished ahead of schedule

FSC PeopleExpand+

  • Martin Simic – Gantry Fabrication Nominated Authority

See how we are helping companies like yours.

Kingfield Galvanising Risk Management and Monitoring Program
Kingfield

Kingfield Galvanising Risk Management and Monitoring Program

Gippsland Line Upgrade Project
Arup

Gippsland Line Upgrade Project

South East Program Alliance – Hallam Level Crossing Removal Project
Laing O'Rourke

South East Program Alliance – Hallam Level Crossing Removal Project

M80 Northern Upgrade Project
MRPV

M80 Northern Upgrade Project

West Gate Tunnel Project – Utilities
CPB Contractors

West Gate Tunnel Project – Utilities

Hazelwood Mine Rehabilitation Project
ENGIE

Hazelwood Mine Rehabilitation Project

CityLink Tulla Widening Gantry Rectification Project
CPB Contractors

CityLink Tulla Widening Gantry Rectification Project

West Gate Tunnel Project – Early Works
CPB JH JV

West Gate Tunnel Project – Early Works