Case Study
Hazelwood Mine Rehabilitation Project
- ClientENGIE
- StartMay 2017
- Value$100m+
- CompleteOngoing
Major project to rehabilitate the Hazelwood power station and mine in the Latrobe Valley, including transforming the mine pit into a lake.
Doing 'it' better
All work delivered within required timeframes, preventing impacts to subsequent activities
FSC Scope
- Bulk earthworks
- Surcharges and benches
- 3km water pipeline to fill pit
- Fire safety water-sourcing pipelines
- Mine security gatehouse
- Extensive drainage and batter stability works
- Landfill capping design and delivery
- Re-engineering a former ash pond into an asbestos containment area
- Eastern overburden dump site investigation
- Developing an EPA-compliant investigation program to inform the site’s environmental water model
Challenges
- Coordinating work across the 4000-hectare site
- Strict construction deadline to start filling the former mine pit with water
- Numerous unrecorded services
- Lean budgets, large production targets and complex interfaces
- A geological profile that often conflicted with actual conditions
- Seasonal weather patterns limiting bulk earthworks to dry months, adding to schedule pressure
Smarts
- Collaborating with the client to proactively understand site conditions and avoid hidden surprises
- Supporting ENGIE to change their systems to those needed for overseeing a massive project with numerous disciplines
- Providing the client with excellent visibility of project performance, forecast cost and completion dates
- Initiation and development of resource levelled integrated program delivery schedule to effectively manage multiple, concurrent projects and interfaces
- Implementation of processes to mitigate against significant scope creep being experienced
- Utilisation of drone surveys providing real-time progress metrics across the large geographic spread of works
Achievements
- Working with the client, designers and EPA on an alternative landfill capping design, saving the client 35% of their initial project budget
- Improved bulk material haul efficiencies resulting in a $2m reduction in costs
- Challenged technical specifications to increase utilisation of in-situ material, further reducing costs by c. $1m
- Saving the client $250,000 by reusing 500m of 750mm diameter steel pipe
- Reducing the extent of in situ pipe welds needed for the Eastern Ring Main Pipeline, saving around $20,000
- Optimising the placement of isolation and scour valves
Performance
- Safety: Zero Lost Time Injuries to date
- Cost: Improved efficiencies preventing the client from realising a forecast $5M overspend
- Program: All work delivered within required timeframes, preventing impacts to subsequent activities
FSC Staff
- Lachlan Smith – Senior Consultant
- David Courtot – Construction Manager
- David Gill – Project Manager
- John Massie – Design Manager
- Stuart Twelftree – Design and Estimating Consultant/Environmental Compliance Manager
- Alex Malesevic – Senior Project Engineer
- Andrew Hines – Senior Project Engineer
- Rory Lamont – Senior Site Engineer
- Dalton Burton – Site Engineer
- James Rodgers – Project Engineer
- Mitch Thomas – Project and Quality Assurance Engineer
- Samuel Wilkinson – Site Engineer
- Matt Powers – Site Engineer
- Tom O’Sullivan – Project Controls Engineer
- Amanda Fontaine – Mine Stability Technician