Case Study

Hazelwood Mine Rehabilitation Project

  • ClientENGIE
  • StartMay 2017
  • Value$100m+
  • CompleteOngoing

Major project to rehabilitate the Hazelwood power station and mine in the Latrobe Valley, including transforming the mine pit into a lake.

Doing 'it' better

All work delivered within required timeframes, preventing impacts to subsequent activities

FSC ScopeExpand+

  • Bulk earthworks
  • Surcharges and benches
  • 3km water pipeline to fill pit
  • Fire safety water-sourcing pipelines
  • Mine security gatehouse
  • Extensive drainage and batter stability works
  • Landfill capping design and delivery
  • Re-engineering a former ash pond into an asbestos containment area
  • Eastern overburden dump site investigation
  • Developing an EPA-compliant investigation program to inform the site’s environmental water model

ChallengesExpand+

  • Coordinating work across the 4000-hectare site
  • Strict construction deadline to start filling the former mine pit with water
  • Numerous unrecorded services
  • Lean budgets, large production targets and complex interfaces
  • A geological profile that often conflicted with actual conditions
  • Seasonal weather patterns limiting bulk earthworks to dry months, adding to schedule pressure

SmartsExpand+

  • Collaborating with the client to proactively understand site conditions and avoid hidden surprises
  • Supporting ENGIE to change their systems to those needed for overseeing a massive project with numerous disciplines
  • Providing the client with excellent visibility of project performance, forecast cost and completion dates
  • Initiation and development of resource levelled integrated program delivery schedule to effectively manage multiple, concurrent projects and interfaces
  • Implementation of processes to mitigate against significant scope creep being experienced
  • Utilisation of drone surveys providing real-time progress metrics across the large geographic spread of works

AchievementsExpand+

  • Working with the client, designers and EPA on an alternative landfill capping design, saving the client 35% of their initial project budget
  • Improved bulk material haul efficiencies resulting in a $2m reduction in costs
  • Challenged technical specifications to increase utilisation of in-situ material, further reducing costs by c. $1m
  • Saving the client $250,000 by reusing 500m of 750mm diameter steel pipe
  • Reducing the extent of in situ pipe welds needed for the Eastern Ring Main Pipeline, saving around $20,000
  • Optimising the placement of isolation and scour valves

PerformanceExpand+

  • Safety: Zero Lost Time Injuries to date
  • Cost: Improved efficiencies preventing the client from realising a forecast $5M overspend
  • Program: All work delivered within required timeframes, preventing impacts to subsequent activities

FSC StaffExpand+

  • Lachlan Smith – Senior Consultant 
  • David Courtot – Construction Manager
  • David Gill – Project Manager
  • John Massie – Design Manager
  • Stuart Twelftree – Design and Estimating Consultant/Environmental Compliance Manager
  • Alex Malesevic – Senior Project Engineer
  • Andrew Hines – Senior Project Engineer
  • Rory Lamont – Senior Site Engineer
  • Dalton Burton – Site Engineer
  • James Rodgers – Project Engineer
  • Mitch Thomas – Project and Quality Assurance Engineer
  • Samuel Wilkinson – Site Engineer
  • Matt Powers – Site Engineer 
  • Tom O’Sullivan – Project Controls Engineer
  • Amanda Fontaine – Mine Stability Technician

See how we are helping companies like yours.

Kingfield Galvanising Risk Management and Monitoring Program
Kingfield

Kingfield Galvanising Risk Management and Monitoring Program

Gippsland Line Upgrade Project
Arup

Gippsland Line Upgrade Project

South East Program Alliance – Hallam Level Crossing Removal Project
Laing O'Rourke

South East Program Alliance – Hallam Level Crossing Removal Project

M80 Northern Upgrade Project
MRPV

M80 Northern Upgrade Project

West Gate Tunnel Project – Utilities
CPB Contractors

West Gate Tunnel Project – Utilities

Hazelwood Mine Rehabilitation Project
ENGIE

Hazelwood Mine Rehabilitation Project

CityLink Tulla Widening Gantry Rectification Project
CPB Contractors

CityLink Tulla Widening Gantry Rectification Project

West Gate Tunnel Project – Early Works
CPB JH JV

West Gate Tunnel Project – Early Works