Case Study

West Gate Tunnel Project – Early Works

  • ClientCPB JH JV
  • StartJuly 2017
  • Value$20m
  • CompleteMarch 2018

Early Works to enable the widening of the West Gate Freeway from 8 to 12 lanes, 6.8km of tunnelling, a bridge over the Maribyrnong River, and 14km of new and improved cycling and walking paths.

Doing 'it' better

Completed within budget, with zero lost-time injuries

FSC ScopeExpand+

  • Geotechnical drilling
  • Environmental sampling
  • Utilities investigations
  • Feature surveys
  • Bathymetry
  • Establishing site compounds
  • Diving works
  • Traffic monitoring
  • Pump testing
  • Design liaison
  • Procurement

ChallengesExpand+

  • Complex stakeholder interface between port, rail and utilities
  • Managing freeway lane closures
  • 7km long worksite with numerous work fronts
  • Few project systems initially in place
  • Extensive night works

SmartsExpand+

  • Planning works to minimise traffic management and disruption
  • Provided permanent sewer to site compounds saving $1.7m compared to temporary connection
  • Connecting permanent power to site compounds saving $1m compared to temporary connection

AchievementsExpand+

  • Rapidly establishing project systems for cost tracking, safety and communication
  • Improving site investigation efficiency allowed M80 area to commence design 6 months early
  • Accelerated the rollout of seven site compounds

PerformanceExpand+

  • Safety: 0 Lost Time Injuries
  • Cost: Completed within budget
  • Program: Completed within Programme

FSC StaffExpand+

  • Lachlan Smith – Early Works Manager
  • Travis Baker – Senior Contract Administrator
  • Chris Ling – Bridge Widening & Site Establishment
  • Alex Malesevic – Design Coordinator Utilities

See how we are helping companies like yours.

Kingfield Galvanising Risk Management and Monitoring Program
Kingfield

Kingfield Galvanising Risk Management and Monitoring Program

Gippsland Line Upgrade Project
Arup

Gippsland Line Upgrade Project

South East Program Alliance – Hallam Level Crossing Removal Project
Laing O'Rourke

South East Program Alliance – Hallam Level Crossing Removal Project

M80 Northern Upgrade Project
MRPV

M80 Northern Upgrade Project

West Gate Tunnel Project – Utilities
CPB Contractors

West Gate Tunnel Project – Utilities

Hazelwood Mine Rehabilitation Project
ENGIE

Hazelwood Mine Rehabilitation Project

CityLink Tulla Widening Gantry Rectification Project
CPB Contractors

CityLink Tulla Widening Gantry Rectification Project

West Gate Tunnel Project – Early Works
CPB JH JV

West Gate Tunnel Project – Early Works