Case Study

West Gate Tunnel Project – Utilities

  • ClientCPB Contractors
  • StartJanuary 2019
  • Value$800m+
  • CompleteJune 2020

Widening the West Gate Freeway from 8 to 12 lanes, 6.8km of tunnelling, a bridge over the Maribyrnong River, and 14km of new and improved cycling and walking paths.

Doing 'it' better

All utility relocation designs completed to tight deadlines, a critical step in enabling permanent works

FSC ScopeExpand+

  • Managing the design process for numerous electrical, gas, water and communications utility relocations in the project’s West Zone
  • Overseeing the designs for relocating 220kV and 22kV/66kV circuits

ChallengesExpand+

  • Congested utility easements
  • Working with construction management team, designers, client and asset owners
  • Developing effective utility relocation designs while fulfilling complex design management processes and industry standards
  • Waterways
  • Soil contamination
  • Stringent stakeholder requirements

SmartsExpand+

  • Helping develop a BIM model for relocating Jemena overhead 22kV and 66kV high voltage circuits near the West Gate Bridge, using 2D drawings of the existing assets
  • Using the 3D model to demonstrate that the utilities could be suspended overhead at Stony Creek rather than bored, simplifying construction and saving the client $6m
  • Safety in Design undertaken prior to preliminary design issue to capture all relevant safety controls and mitigate potential redesign

AchievementsExpand+

  • All utility relocation designs were completed to the tight deadlines – a critical step in enabling permanent works
  • To meet timelines and reduce the number of re-designs, the team produced design alignments in-house instead of relying on the utility providers. This allowed relocation designs for Ausnet’s 220kV HV assets to be completed in just 3 months, after having previously been stuck in preliminary design for a year.

PerformanceExpand+

  • Safety: 0 Lost Time Injuries
  • Program: All designs were Issued for Construction at least 10 days prior to construction commencing

FSC StaffExpand+

  • Adrian Khor – Design Manager
  • Alex Malesevic – Utilities Design Coordinator
  • James Rodgers – Utilities Design Coordinator
  • Jacob Ostwald – BIM Coordinator – Utilities

See how we are helping companies like yours.

Kingfield Galvanising Risk Management and Monitoring Program
Kingfield

Kingfield Galvanising Risk Management and Monitoring Program

Gippsland Line Upgrade Project
Arup

Gippsland Line Upgrade Project

South East Program Alliance – Hallam Level Crossing Removal Project
Laing O'Rourke

South East Program Alliance – Hallam Level Crossing Removal Project

M80 Northern Upgrade Project
MRPV

M80 Northern Upgrade Project

West Gate Tunnel Project – Utilities
CPB Contractors

West Gate Tunnel Project – Utilities

Hazelwood Mine Rehabilitation Project
ENGIE

Hazelwood Mine Rehabilitation Project

CityLink Tulla Widening Gantry Rectification Project
CPB Contractors

CityLink Tulla Widening Gantry Rectification Project

West Gate Tunnel Project – Early Works
CPB JH JV

West Gate Tunnel Project – Early Works