Case Study
M80 Northern Upgrade Project
- ClientMRPV
- StartOctober 2021
- Value$518m
- CompleteApril 2022
The M80 Northern added new lanes between Sydney Road and Edgars Road, a smart freeway lane management system, and new on- and off-ramps
Doing 'it' better
Upgrading the M80 between Sydney and Edgars roads, including widening and realigning ramps
FSC Scope
- Constructing pavements, noise walls, barriers, guard fences and footpaths
- Programming, cost tracking, procurement and safety reporting
- Subcontractor management, including claims, program integration and resourcing
- Design liaison
- Developing traffic management plans
- Overseeing close-out of work-lots, defects and contracts
Achievements
- Despite COVID impacts and multiple packages needing to be completed simultaneously, FSC completed works ahead of program and achieved all inspection KPIs
- Traffic management minimised disruption to public while maintaining traffic volumes
- No delays to the public during traffic switching campaigns
- Gained approval to reduce earthworks testing frequency, reducing costs and potential delays
- All work-lots closed-out before scheduled finish date