Yallourn Power Station - PFAS Remediation

A historic fire-fighting training area at Yallourn Power Station required soil remediation to address PFAS contamination levels that exceeded acceptable ecological investigation standards.

Services Provided

  • Review of previous environmental investigation findings
  • Development of a technical specification aimed at removing approximately 90% of the PFAS contaminant mass in the soil
  • Site setup and marking of the designated excavation area
  • Excavation of contaminated materials from the identified remediation site
  • Loading, treatment, and disposal of material at a landfill licensed to handle PFAS waste
  • Refilling the excavated area to meet civil engineering requirements

Client

Ventia Environmental Services

Location

Hazelwood, Victoria

Year

2023

Image of architecture

A historic fire-fighting training area at Yallourn Power Station required soil remediation to address PFAS contamination levels that exceeded acceptable ecological investigation standards.

Services Provided

  • Review of previous environmental investigation findings
  • Development of a technical specification aimed at removing approximately 90% of the PFAS contaminant mass in the soil
  • Site setup and marking of the designated excavation area
  • Excavation of contaminated materials from the identified remediation site
  • Loading, treatment, and disposal of material at a landfill licensed to handle PFAS waste
  • Refilling the excavated area to meet civil engineering requirements

Related

View All
Image of sign

South-Eastern Program Alliance

  • Contaminated Land Consulting
  • Transport
Image of terminal

Suburban Rail Loop East - Work Packages A & B

  • Contaminated Land Consulting
  • Environmental Advisory
  • Transport
Image of road

Narre Warren-Cranbourne Road

  • Sustainability Advisory
  • Contaminated Land Consulting
  • Environmental Advisory
  • Transport